When to run the utility
Describes the circumstances in which you would use the data capture utility.
Use
the data capture utility in
these circumstances:
- An IBM Workload Scheduler process has failed, but the automatic ffdc facility has not detected the failure and run the script for you (see First failure data capture (ffdc))
- IBM Workload Scheduler is very slow or is behaving in any other abnormal way
- You are requested to do so by IBM® Software Support
Using the utility when you need to switch to the backup master domain manager
If the master domain manager fails you might decide that you want to switch to the backup master domain manager to keep your scheduling activities running. If you also want to run the data capture utility you have two choices:- Data capture first
- Run the data capture utility first to ensure that the information extracted is as fresh as possible. Then run switchmgr.
- Switchmgr first
- In an emergency situation, where you must continue scheduling activities, run switchmgr immediately and then run the data capture utility on both the new master domain manager and the new backup master domain manager as soon as switchmgr has completed.