Keeping plans up-to-date

About this task

When you have changed the current plan, or when the duration of some work has varied significantly from its schedule, the planned times in the current schedule might be inaccurate. To make IBM Z Workload Scheduler recalculate these times, taking the current information into account, replan the current plan. You can do this in two ways:
  1. Enter the Replan panel from the DAILY PLANNING panel, by selecting the 1 (REPLAN) option on the PRODUCING OPC DAILY PLANS panel. The scheduler will then submit the replan job.
  2. Define the replan job as an application in IBM Z Workload Scheduler so you can schedule the replan as you would any other application, and IBM Z Workload Scheduler will submit it automatically.

The REPLAN job removes all completed occurrences from the current plan panels.