Changing the stage duration during a run

Increase or decrease the duration of the current stage during a schedule run. You can change the duration of a stage that is set to run for a specified time, but not for a stage that is set to run until the work is complete. You can change the duration of a stage when the status is Running, but not when the status is Ramping or Settle Time.

Before you begin

Procedure

  1. From the test editor, click Run Test. The execution report is opened either in the internal or external browser, and the state of the run is shown as Running.
  2. During the run, click Running > Change current stage duration.
  3. In the Change Stage Duration window, type the new stage duration in Run for specified period of time. Type a value that is longer than the amount of time that has elapsed for the current stage. Use the list to change the time units.
  4. Click Change.
    The duration of the current stage changes.