Converting JMeter tests to VU schedule
You can convert a JMeter test to a VU schedule to load and test the performance of an application under test.
About this task
Rational® Performance Tester analyzes the selected JMeter test to add the number of users and loop iteration count in the VU schedule. When you convert the JMeter test to a VU schedule, the following events occur:
-
The load information identified within the Thread Group nodes from the original JMeter test is examined to build a new VU schedule.
-
The content of each Thread Group node is extracted from the original JMeter test and copied into a new JMeter test.
-
The new JMeter test is then invoked by the VU schedule as an external test.
Note: The extracted JMeter test does not contain any load information such as the number of users and loop count, because the VU schedule manages all the information.
-
The content of the original Thread Group is not considered during the conversion process. Therefore, if there are any loops in the JMeter Thread Group, those cannot convert into a loop element in the new VU schedule.
-
If you have a JMeter test with more than one Thread Group node, each Thread Group is extracted to separate the JMeter test.
-
If you have a complex JMeter test, you must extract the functionalities that are included in the Modules or Include controllers into another JMeter tests. You must then add those JMeter tests to a VU schedule to run it.
Procedure
- Browse and select the JMeter test from the Test Navigator.
- Right-click the selected test, and then click Convert to VU Schedule.
- Verify that the name of the schedule is same as name of the JMeter test.
-
Click Finish.
The schedule editor opens.
What to do next
You must perform the following tasks:
Run the converted test assets against successive builds of the application under test. See Running a local schedule or test.